Overview
Overview
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | 1 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| 11 Campbell KrishviRegistered · no quarterly update yet | KRISHVI PROJECTS PRIVATE LIMITED | Apartment | 1,888 sqft carpet (as filed) | Dec 2026 |
| Aashrithaa Divine Phase - 2Completed (regulator flag) | AASHRITHAA PROPERTIES PRIVATE LIMITED | Plot | – | Completed |
| CelestiaLapsed · completion date passed | PYRAMID PROPERTIES | Apartment | – | May 2022 |
| Chartered 1956Active · 95% built | CHARTERED HOUSING PRIVATE LIMITED | Apartment | 2,988 sqft carpet (as filed) | Jun 2028 |
| Comfort VimalaprabhaLapsed · completion date passed | COMFORT BUILDERS & DEVELOPERS | Apartment | – | Sep 2024 |
| Df Silverline Queens TerracesCompleted · OC 18-07-2018 | DF SILVERLINE CONSTRUCTIONS | Apartment |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
₹99 for this report opens Contract & costs and Disputes & cases for this project, yours to read for good.
Contract & costs
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
What we read
Source: K-RERA project page and the documents filed there, as read by us. 21 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Location & risks | – | – | – | – |
|---|
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| 1,380 sqft carpet (as filed) |
| Completed |
| Embassy Habitat | Embassy Group | Apartment | 1,100–3,427 sqft | – |
| Emmanuel Ashley ParkLapsed · completion date passed | EMMANUEL ESTATES | Apartment | 831 sqft carpet (as filed) | Dec 2024 |
8 of 32 other projects in Vasanth Nagar, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Saibya Sundew in the interactive atlas
Approval or registration
Land use converted
Deputy Commsisioner · Survey 61/7
K-RERA filing, land schedule
Approval or registration
Khata issued
A Khatha · BBMP · Survey 61/7
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BBMP · plan BBMP/AD.COM./BMH/0446/20-21
K-RERA filing, approvals
Approval or registration
RERA registration
PRM/KA/RERA/1251/310/PR/021222/005496
K-RERA registration ·
Approval or registrationTransfer of the landThe parcels join the project
Read from the original documentDescribed in the filing or another document; the original is not read here
| Charges on the land | Not verified yet | |
|---|---|---|
| Developer's project loan | None declared | |
| Mortgage on the project land | None declared | |
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Survey numbers | 61/7 | |
|---|---|---|
| Land extent, Sy 61/7 | 1 Acre | |
| Area on the KGIS map | Not verified yet | |
| Land area of this registration | 3,276 sq m | |
| Khata | A Khatha · BBMP · 16 Nov 2017 | |
| Sale deed | 6 Sep 2017 | |
| Building plan (BBMP) | Sanctioned 26 Apr 2021 · No. BBMP/AD.COM./BMH/0446/20-21 | |
|---|---|---|
| Power NOC (BESCOM) | Not verified yet | |
| Fire department | Filed with the registration | |
| SEIAA | Filed with the registration | |
| AAI | Filed with the registration | |
| Pollution board (CFE) | consent order W-126189 · issued 3 Feb 2024 | |
| Water and sewerage NOC (BWSSB) | issued 27 Sep 2022 | |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 28 Feb 2025 |
| Land conversion | Converted 28 Nov 2005 · Deputy Commsisioner | |
|---|---|---|
| Survey numbers | 61/7 |
₹99 for this report opens Contract & costs and Disputes & cases for this project, yours to read for good.
flats · avg 75 m² 100%
| Type | Flats | Carpet per flat, average (sq ft) |
|---|---|---|
| flats | 72 | 811 |
| Vista Svara | about 2 km | Locked | |
|---|---|---|---|
| Vista Padmalaya | about 3.5 km | Locked | |
| Renaissance Srichakra | about 4 km | Locked | |
| Birla Tisya | about 5 km | Locked | |
| Magnolia Delight | about 5.5 km | Locked |
| Saibya Sundew This project | This project is the point the others are measured from | 28 Feb 2025 | Not filed | Not verified yet |
|---|---|---|---|---|
| Vista Svara | about 2 km | 30 Oct 2026 | 50% (16 of 32) | Locked |
| Vista Padmalaya | about 3.5 km | 30 Apr 2027 | 40% (4 of 10) | Locked |
| Renaissance Srichakra |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | Not verified yet | |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | about 0.5 km, KR circle Underpass | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | about 1 km, secondary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 1 km, an unnamed water body | |
| Height above nearest drain | Not verified yet | |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Amenities declared | Electricity · CCTV Surveillance · Community Hall · Gym · Power Backup · Water and Sanitation | |
|---|---|---|
| Kitchen handover | Not verified yet | |
| Covered parking per unit | 1.00 (72 covered spaces for 72 units) | |
| Sewage plant | Sewage treatment plant | |
| Power backup | Declared by the promoter | |
Ten-year July mean for this taluk: 26.8 m
Across Bengaluru North, the water table sat 22.7 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 26.8 m, and it fell 4.9 m over the year.
| Groundwater | Bengaluru North taluk average, July 2023: 22.7 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 22.7 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Borewell | |
| Nearest city water main | Not verified yet | |
| Main structure | Not verified yet | |
|---|---|---|
| Electrical and plumbing finishing | Not verified yet | |
| Internal roads | Not verified yet | |
| Club house | Not verified yet | |
| Completion | Completed, occupancy certificate 2 May 2024 | |
| Completion, accountant | Not verified yet | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | 31 Jan 2024 | |
| RERA completion date | 28 Feb 2025 | |
| Work began, as filed | 1 Nov 2021 | |
| Structure | RCC framed structure | |
|---|---|---|
| Foundation | Not verified yet | |
| Wall material | Not verified yet | |
| Wall thickness | Not verified yet | |
| Concrete / steel grade | Not verified yet | |
| Building heights, fire NOC | 14.4 m filed, 2 towers | |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Windows | UPVC windows | |
|---|---|---|
| Flooring | Vitrified tiles | |
| Toilet tiles | Ceramic tiles (walls, up to 7 feet) | |
| Wiring | Not verified yet | |
| Sanctioned load per flat | Not verified yet | |
| Power backup | 100% power backup for common areas | |
| Sewage plant | Sewage treatment plant | |
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Not verified yet | |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | Not verified yet | |
| Environmental clearance | Not verified yet | |
| Chartered accountant's certificate, registration | Dated 18 May 2022 | |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
| Estimated cost | ₹19.10 Cr | |
|---|---|---|
| Cost incurred | Not verified yet | |
| Cost left | Not verified yet | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | Not verified yet | |
| Land cost revision | Not verified yet | |
Sold (36) 50%Unsold (36) 50%
| Flats sold, at completion | 36 | |
|---|---|---|
| Flats unsold, at completion | 36 | |
| Flats in the phase | 72 |
| Escrow bank | HDFC · J P NAGAR | |
|---|---|---|
| Designated account, collected | Not verified yet | |
| Designated account, withdrawn | Not verified yet | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan (BBMP) | Sanctioned 26 Apr 2021 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | HDFC · J P NAGAR | |
| Ranka Iris | about 5.5 km | Locked |
|---|
| Adarsh Premia | about 6.5 km | Locked |
|---|
| Century Regalia (Project 2) | about 7 km | Locked |
|---|
| Aydin Infra Signature 3 | about 8 km | Locked |
|---|
| Sobha Royal Crest | about 8 km | Locked |
|---|
| Song Of Wind | about 8.5 km | Locked |
|---|
| Pacific Legacy | about 8.5 km | Locked |
|---|
| about 4 km |
| 11 Aug 2027 |
| 63% (5 of 8) |
| Locked |
| Birla Tisya | about 5 km | 31 Dec 2026 | 100% (392 of 392) | Locked |
|---|
| Magnolia Delight | about 5.5 km | 31 Mar 2028 | 21% (10 of 48) | Locked |
|---|
| Ranka Iris | about 5.5 km | 30 Apr 2026 | 62% (8 of 13) | Locked |
|---|
| Projects within 4 km, counted | 22 (22 with an approximate location) | |
|---|---|---|
| Flats in them | 1,299 | |
| Booked | 1,004 of 1,299 (77%) | |
| Unsold | 295 | |
| Booked a month, pooled | 10 flats | |
| Months to sell, pooled | 28 months |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | about 1 km, secondary drain | |
| Ground level | Not verified yet | |
| Metro, operational | about 0.5 km, Sir M. Visvesvaraya Stn., Central College | |
| Metro, under construction | Not verified yet | |
| Kempegowda Airport | 34.5 | 28 |
| MG Road (CBD) | 4 | 2 |
| Manyata Tech Park | 11 | 8.5 |
| ITPL, Whitefield | 21 | 16.5 |
| Ecospace, Bellandur ORR | 17.5 | 12 |
| Electronic City Ph 1 | 22 | 18.5 |
| Landfill or waste transfer station | about 1.5 km | |
|---|---|---|
| Sewage treatment plant | about 1 km, named Cubbon Park 4MLD Sewage Treatment Planet on OpenStreetMap | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 1 km, named Kanteerava Stadium on OpenStreetMap |