| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | 2 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
Part of the full report. Unlock all 5 sections
| 1 Lakh Multi Storey Bengaluru Housing BidarahalliLapsed · completion date passed | Rajiv Gandhi Housing Corporation Limited | Apartment | 323 sqft carpet (as filed) | Mar 2024 |
| 2g TulaExtended to 27-12-2027 | Togetherments Infra Pvt Ltd | Apartment | 1,256–1,485 sqft carpet (as filed) | Dec 2027 |
| A M RajshekarActive · 70% built | A M RAJSHEKAR | Plot | ~600–1,200 sqft (estimate: filed carpet plus 25%) | Dec 2028 |
| Aakruthi Roots & RaysCompleted (regulator flag) | AAKRUTHI PROPERTIES | Plot | ~980–1,800 sqft (estimate: filed carpet plus 25%) | Completed |
| Aasara GreenwoodsCompleted · OC 02-04-2025 | AASARA BUILDERS | Apartment | 1,665–2,497 sqft carpet (as filed) | Completed |
| Adarsh Palm Meadows | Adarsh Developers | Villa | 1,800–5,500 sqft | – |
Title & ownership
Approvals
Disputes & cases
Contract & costs
Valuation
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
215 documents filed with K-RERA for this project
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Valuation |
|---|
| – |
| – |
| – |
| Locked |
| Location & risks | – | – | – | – |
|---|
| Construction & progress | – | – | 1 | Clear |
|---|
| Developer & finance |
|---|
| Developer | – | 1 | – | Review |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Adithya EsquinaCompleted · OC 21-03-2019 | ADITHYA CONSTRUCTIONS | Apartment | 884 sqft carpet (as filed) | Completed |
| Adithya Green GardensCompleted · OC 14-06-2022 | ADITHYA DEVELOPERS | Apartment | 880–1,095 sqft carpet (as filed) | Completed |
8 of 396 other projects in Whitefield, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Kumari Nautilus in the interactive atlas
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Building plan (BMRDA) | Sanctioned 12 Jan 2023 · No. STRRPA/TP/DP/04/2022-23 | |
|---|---|---|
| Power NOC (BESCOM) | Filed with the registration | |
| Fire department | Filed with the registration | |
| Environmental clearance (1 of 2) | SEIAA 69 CON 2022 · EC identification no. EC22B038KA134286 · issued 22 Aug 2022 | Clear |
| Environmental clearance (2 of 2) | SEIAA 69 CON 2021 | |
| Airport height NOC | Filed with the registration | |
| Pollution board (CFE) | Filed with the registration | |
| Water supply NOC | Filed with the registration |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 12 Jan 2028 |
| Land conversion | Converted 31 Jul 2021 · Deputy Commissioner | |
|---|---|---|
| Survey numbers | 40/1 · 40/2 · 40/3 · 40/4 · 40/5 · 41/1 · 41/5 · 41/6 · 41/7 |
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
₹99 for this report opens Valuation, Contract & costs, Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | Not verified yet | |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | about 3 km, SIDDHARTHA LAYOUT KADUGODI | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | about 1.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed water body | |
| Height above nearest drain | Not verified yet | |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Amenities declared | Electricity · Community Hall · Indoor Sports facility · Gym · Water and Sanitation | |
|---|---|---|
| Electricity, built | 85% | |
| Community Hall, built | 40% | |
| Indoor Sports facility, built | 20% | |
| Gym, built | 0% | |
| Water and Sanitation, built | 40% | |
| Kitchen handover | Not verified yet | |
| Covered parking per unit | 1.24 (204 covered spaces for 165 units) | |
| Sewage plant | Not verified yet | |
| Power backup | Not declared | |
Ten-year July mean for this taluk: 62 m
Across Hosakote, the water table sat 22.6 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 62 m, and it recovered 4.9 m over the year.
| Groundwater | Hosakote taluk average, July 2023: 22.6 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 22.6 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Borewell, Local authority (Samathanahalli Gram Panchyat) | |
| Nearest city water main | Not verified yet | |
| Landfill or waste transfer station |
|---|
As the promoter reported it

| Main structure | 100% · planned by 9 Jun 2024 | |
|---|---|---|
| Electrical and plumbing finishing | 80% · planned by 19 Jan 2026 | |
| Internal roads | Not verified yet | |
| Club house | Not verified yet | |
| Completion | 90% | |
| Completion, accountant | Not verified yet | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | 19 Jan 2026 | |
| RERA completion date | 12 Jan 2028 | |
| Work began, as filed | 12 Jan 2023 | |
| Structure | Not verified yet | |
|---|---|---|
| Foundation | Not verified yet | |
| Wall material | Not verified yet | |
| Wall thickness | Not verified yet | |
| Concrete / steel grade | Not verified yet | |
| Building heights, fire NOC | 10.35 m filed | |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Windows | Not verified yet | |
|---|---|---|
| Flooring | Not verified yet | |
| Toilet tiles, spec vs brochure | Not verified yet | |
| Wiring | Not verified yet | |
| Sanctioned load per flat | Not verified yet | |
| Power backup | Not provided | |
| Sewage plant | Not verified yet | |
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Form 6 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | Not verified yet | |
| Environmental clearance (1 of 2) | SEIAA 69 CON 2022 · EC identification no. EC22B038KA134286 · issued 22 Aug 2022 | |
| Environmental clearance (2 of 2) | SEIAA 69 CON 2021 | |
| Architect, quarterly | Form 5 · Jan 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | |
| Architect's certificate, registration | Dated 31 Jan 2023 · site inspected 5 Jan 2023 | |
| Chartered accountant's certificate, registration | Dated 10 Feb 2023 | |
Page 1
Page 1 of the structural safety certificate. The promoter filed this with the registration.
Land · ₹21.67 Cr 12.2%Development · ₹155.66 Cr 87.8%
| Estimated cost | ₹177.33 Cr | |
|---|---|---|
| Estimated cost, architect's certificate | ₹120.11 Cr | |
| Cost incurred | Not verified yet | |
| Cost left | ₹18.45 Cr | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | Not verified yet | |
| Land cost revision | Not verified yet | |
Sold (114) 69.1%Unsold (51) 30.9%
| Sold, Q3 2025-26 | 112 / 165 · 53 available | |
|---|---|---|
| Sold, Q4 2025-26 | 113 / 165 · 52 available | |
| Sold, Q1 2026-27 | 114 / 165 · 51 available | |
| Sold, Q2 2026-27 | 114 / 165 · 51 available | |
| Unsold, Q2 2026-27 | 51 | |
| Sold in Q4 2025-26 | 1 | |
| Sold in Q1 2026-27 | 1 | |
| Sold in Q2 2026-27 | 0 | |
| Flats booked, Form 4 Q1 2026-27 | 113 |
| Escrow bank | INDUSIND BANK · MUSEUM ROAD (CHURCH STREET) | |
|---|---|---|
| Designated account, collected | ₹6.39 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹4.23 Cr in Q2 2026-27 (66% of that quarter's deposits) | |
| Share of collections deposited in escrow | 70% | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan (BMRDA) | Sanctioned 12 Jan 2023 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | INDUSIND BANK · MUSEUM ROAD (CHURCH STREET) | |

Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | about 1.5 km, tertiary drain | |
| Ground level | Not verified yet | |
| Metro, operational | about 3.5 km, Whitefield | |
| Metro, under construction | Not verified yet | |
| Kempegowda Airport | 41 | 24.5 |
| MG Road (CBD) | 25.5 | 20.5 |
| Manyata Tech Park | 25 | 19.5 |
| ITPL, Whitefield | 7.5 | 6 |
| Ecospace, Bellandur ORR | 18 | 14.5 |
| Electronic City Ph 1 | 31.5 | 21.5 |
| None within 3 km |
| Sewage treatment plant | about 1.5 km, named Kadugodi 6MLD Sewage Treatment Planet on OpenStreetMap |
|---|
| Quarry | None within 3 km |
|---|
| Crematorium | None within 3 km |
|---|
| Prison | None within 3 km |
|---|
| Electrical substation | None within 3 km |
|---|