| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | 1 | Clear |
| Disputes & cases | – | – | – | – |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | 1 | – | |
| 2 Oakland EstatesFiled as completed · no completion certificate on record | DEAMANTE PROPERTIES | Plot | ~1,500 sqft (estimate: filed carpet plus 25%) | Aug 2022 |
| Aarohana AdiraActive · 5% built | AAROHANA PROJECTS | Apartment | 776–1,745 sqft carpet (as filed) | Dec 2030 |
| Adarsh Savana Phase 1Lapsed · completion date passed | SHRESHTA INFRA PROJECTS PRIVATE LIMITED | Plot | – | Oct 2023 |
| Adarsh Savana Phase 2Registered · no quarterly update yet | ALEKHYA PROPERTY DEVELOPMENTS PVT LTD. | Plot | ~1,200–3,190 sqft (estimate: filed carpet plus 25%) | Jun 2029 |
| Aditya Palm GroveApplied for completion 05/12/2019 | SRI ADITYA HOMES PRIVATE LIMITED | Plot | – | Dec 2019 |
| Aero ExoticLapsed · completion date passed | LOTUS ENCLAVE |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Approvals
Disputes & cases
Builder: SAI BHARATHI RESORTS PRIVATE LIMITED
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Not checked. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Not checked. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None found. | ||||||
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None found. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
Loan & collateral
Data room
Source: K-RERA project page and the documents filed there, as read by us. 21 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Review |
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Plot |
| ~1,200–1,530 sqft (estimate: filed carpet plus 25%) |
| Dec 2023 |
| Aeropolis, A Project Of Sattva GroupLapsed · completion date passed | TRINAYANI REALTOR PRIVATE LIMITED | Apartment | 280–635 sqft carpet (as filed) | Jul 2026 |
| Aira HillsApplied for completion 17/02/2026 | Vaarahi Developers Pvt Ltd | Plot | – | Dec 2024 |
8 of 263 other projects in Devanahalli, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Gokula Square in the interactive atlas
Transfer of the land
Sale deed
in favour of SAI BHARATHI RESORTS PRIVATE LIMITED · Survey 228/1
K-RERA filing, land schedule
Approval or registration
Land use converted
DC BANGALORE RURAL · Survey 228/1
K-RERA filing, land schedule
Approval or registration
Building plan sanctioned
BIAPPA · plan BIAAPA/TP/LAO/154/2025-26
K-RERA filing, approvals
Approval or registration
Khata issued
3 Acre, 9 Gunta · NA · Survey 228/1
K-RERA filing, land schedule
Approval or registration
RERA registration
PRM/KA/RERA/1250/303/PR/280726/008852
K-RERA registration
Transfer of the landApproval or registrationThe parcels join the project
Described in the filing or another document; the original is not read here
Survey plots around the filed site pin, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around the filed site pin. This project's survey numbers are not matched to them yet, so no plot is marked as its land.
| Survey numbers | 228/1 | |
|---|---|---|
| Land extent, Sy 228/1 | 3 Acre, 9 Gunta | |
| Area on the KGIS map | Not verified yet | |
| Khata | 3 Acre, 9 Gunta · NA · 15 Jun 2026 | |
| Sale deed | Dated 22 Dec 2025 | |
| Sale deed in favour of | SAI BHARATHI RESORTS PRIVATE LIMITED | |
| Building plan (BIAPPA) | Sanctioned 23 Feb 2026 · No. BIAAPA/TP/LAO/154/2025-26 | |
|---|---|---|
| Power NOC (BESCOM) | Filed with the registration | |
| Fire NOC | Not verified yet | |
| SEIAA | Filed with the registration | |
| Airport height NOC | Not verified yet | |
| KSPCB | Filed with the registration | |
| Water supply NOC | Filed with the registration | |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 1 Jun 2026 |
| Land conversion | Converted 7 Jan 2026 · DC BANGALORE RURAL | |
|---|---|---|
| Survey numbers | 228/1 |
| Ekta Elements | 9.0 km | Locked |
|---|
| Gokula Square This project | This project is the point the others are measured from | 1 Jun 2026 | Not filed | Not verified yet |
|---|---|---|---|---|
| Ekta Elements | 9.0 km | 31 Dec 2027 | Not filed | Locked |
| Rent per sq ft, 3 km | ₹20.3 /mo, as listed · 7 listings with a size | |
|---|---|---|
| Gross yield | Not verified yet | |
| Gross yield, per sq ft | Not verified yet | |
| Bengaluru median yield | Not verified yet | |
Map of the ground within about 900 m of the site, showing high-tension power lines, storm drains and government-flagged flood locations.
| Zoning, RMP 2015 | Transport & communication, at the filed pin | |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | 20.4 km, Shankrappa Layout, MAruthi nagar | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | 320 m to the south-west, an unnamed water body | |
| Height above nearest drain | Not verified yet | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | Not verified yet | |
| RERA completion date | 1 Jun 2026 | |
| Work began, as filed | 23 Feb 2026 | |
Land · ₹28.85 Cr 92.7%Development · ₹2.29 Cr 7.3%
| Estimated cost | ₹31.14 Cr | |
|---|---|---|
| Cost incurred | Not verified yet | |
| Cost left | Not verified yet | |
| Collected from buyers | Not verified yet | |
| Receivable, sold plots | Not verified yet | |
| Land cost revision | Not verified yet | |
| Escrow bank | Not verified yet | |
|---|---|---|
| Designated account, collected | Not verified yet | |
| Designated account, withdrawn | Not verified yet | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
| Developer's project loan |
|---|
| Not verified yet |
| Records searched to | Not verified yet | |
|---|---|---|
| Building plan (BIAPPA) | Sanctioned 23 Feb 2026 |
|---|
| Unregistered agreements, over 10% paid | Not verified yet | |
|---|---|---|
| Sale deed in favour of | Not verified yet | |
|---|---|---|
| Escrow bank | Not verified yet | |
|---|---|---|
| Projects within 4 km, counted | 14 (6 with an approximate location) | |
|---|---|---|
| Flats in them | 3,645 | |
| Booked | 2,702 of 3,645 (74%) | |
| Unsold | 943 | |
| Booked a month, pooled | 46 flats | |
| Months to sell, pooled | 16 months |
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
Ten-year July mean for this taluk: 32.6 m
Across Devanahalli, the water table sat 19.3 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 32.6 m, and it recovered 10.2 m over the year.
| Groundwater | Devanahalli taluk average, July 2023: 19.3 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 19.3 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Borewell, Local authority (DEVANAHALLI PURASABE) | |
| Nearest city water main | 15.9 km | Review |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the site, with rings at 1 km and 3 km.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | None within 3 km | |
| Ground level | Not verified yet | |
| Metro, operational | Not verified yet | |
| Metro, under construction | 6.0 km, KIA Terminal | |
| Kempegowda Airport | 11.9 | 15 | 6.1 |
| MG Road (CBD) | 37.3 | 38 | 33.2 |
| Manyata Tech Park | 32.5 | 34 | 25.3 |
| ITPL, Whitefield | 41.5 | 38 | 29.7 |
| Ecospace, Bellandur ORR | 52.1 | 51 | 36.5 |
| Electronic City Ph 1 | 57.1 | 62 | 46.1 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | 1.6 km to the south-east | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | 660 m to the north-east |