Building plan (Local Planning Authority)Sanctioned 5 Apr 2023No. LAO/138/22-23/05-04-2023
RERA extensionsGranted!ReviewReview
RERA complaints0✓ClearClear
Land conversionConverted, 2 of 2 parcelsDates and authorities below
Permits
Validity
Not verified yet
Disputes & cases
Are there court cases or buyer complaints on this project?
Locked
Cases on the landNo cases
Cases on the builderNo cases
RERA complaintsNo cases
Builder's other projectsNo cases
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
Contract & costs
What does a buyer commit to?
Locked
Forfeiture, agreement•• %
Forfeiture, allotment letterNot verified yet
Transfer feeNot verified yet
Maintenance includedNot verified yet
Cancellation
Forfeiture
Not verified yet
Agreement and allotment letter
Valuation
What is it worth?
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Recent price, super built-upNot verified yet
Recent price, carpetNot verified yet
Phase 1 → Phase 2Not verified yet
Gross yield, per sq ftNot verified yet
This project
Price
Price per sq ft, super built-up
Location & risks
What is the location like?
Height above nearest drainNot verified yet
Groundwater, taluk average21.3 m below groundAnekal taluk, July 2023
Water supply, as filedBWSSBDeclared by the promoter
Metro, under constructionabout 12 kmKodibeesanahalli, under construction
The site
Construction & progress
How is it being built, and when will it be ready?
Review1 to review · 1 clear
Completion39%As of Q3 2025-26, promoter's return
Possession, agreement31 Dec 2026Agreement for sale, p. 9
StructureNot verified yet
Structural safety certificateNot verified yet
Progress
Completion, architect
Developer
Can the developer deliver?
Receivable, sold flatsNot verified yet
Cost leftNot verified yet
Sold8 / 40As of Q3 2025-26
Sold in the latest quarterNot verified yet
Funding
Estimated cost
Loan & collateral
Can it be financed?
Value, 3BHK ANot verified yet
Max loan, 3BHK ANot verified yet
Borrower marginNot verified yet
Developer's project loanNo borrowing declaredAs declared in the K-RERA filing
Value & LTV
3BHK A
Not verified yet
Calculation
Not verified yet
Conditions
Collateral checks
Data room
Documents filed for this project
Documents filed151On K-RERA
Available151100% of filed
K-RERA only0
Approvals with a validity dateNone read
Approvals & NOCs
Available
Available
Available
2 pagesAvailable
Available
Available
Available
Available
Available
9 pagesAvailable
Available
Available
Available
Available
Available
Available
Available
Available
Filed 17 Dec 20233 pagesAvailable
Filed 12 Jan 20241 pageAvailable
Source: K-RERA project page and the documents filed there, as read by us. 31 documents filed with K-RERA, identity papers and photographs, are left out of this list.
Unlock this full report₹99 for this report · opens Contract & costs, Title & ownership and Disputes & casesUnlock
Imagery: Esri, Vantor, Earthstar Geographics
Satellite map with the 1 cadastral survey plot named in the filing outlined. The outline is the land, not the building. The 1 filed survey number matched. Survey numbers read from the filed land documents and checked against the cadastre by an independent reviewer, 9 Oct 2026.
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Approximate location: the filed pin, good to the neighbourhood, not the plot
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Dream Scape in the interactive atlas
•• ••• ••••
Title
Title report
•• %
•• ••• ••••
•••••
₹ •.•• Cr
Charges
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
Boundaries
Schedule in the EC vs KGIS neighbours
Not verified yet
Encumbrance certificate, Form 15
Survey sketch
Survey sketch filed with K-RERA
Not verified yet
Sketch, sanction and mutation vs KGIS map
₹ ••,•••
•• %
•• ••• ••••
•••••
Land record
Survey plots · KGIS cadastral
Filing vs KGIS map
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
The RTC of each filed survey
Not verified yet
Ownership
Share of sales revenue
Not verified yet
Joint development agreement
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unlock this full report
₹99 for this report opens Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Storm drain, primary
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Lake or tank
Storm drain, primary
Storm drain, smaller
Approximate location: the filed pin, good to the neighbourhood, not the plot
Electricity · CCTV Surveillance · Community Hall · Gym · Power Backup · Water and Sanitation
Club House, built
30%
Electricity, built
30%
Outdoor Sports facility, built
30%
Gym, built
30%
Water and Sanitation, built
30%
Kitchen handover
Not verified yet
Covered parking per unit
1.85 (74 covered spaces for 40 units)
Sewage plant
Not verified yet
Power backup
Declared by the promoter
Around it
Water
Groundwater, Anekal taluk average
Ten-year July mean for this taluk: 28.7 m
Across Anekal, the water table sat 21.3 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 28.7 m, and it recovered 3.3 m over the year.
Water at a glance
Groundwater
Anekal taluk average, July 2023: 21.3 m below ground
What it means
Not verified yet
Water below ground
21.3 m, the taluk average
Through the year
Not verified yet
Water supply, as filed
BWSSB
Nearest city water main
Not verified yet
Distances
Within 3 km of the filed pin
Connectivity
Road distance from the site
Nuisances
Distance from the filed pin
DOSL nuisance layer
Landfill or waste transfer station
None within 3 km
Not verified yet
Site photos filed with K-RERA, Q3 2025-26
Work left
By component, Q3 2025-26
Quarterly return, Q3 2025-26
Main structure
100% · planned by 31 Mar 2024
Electrical and plumbing finishing
35% · planned by 1 Aug 2025
Internal roads
Not verified yet
Club house
30%
Completion
39%
Completion, accountant
Not verified yet
Dates
Dates
Filed dates
Possession, agreement
31 Dec 2026
Schedule end
31 Aug 2025
RERA completion date
31 Aug 2026
!Review
Work began, as filed
1 Dec 2023
Specified structure
What the promoter specified · not an inspection
Structure
Not verified yet
Foundation
Not verified yet
Wall material
Not verified yet
Wall thickness
Not verified yet
Concrete / steel grade
Not verified yet
Building heights, fire NOC
12.15 m filed
Specification sheet, page 1
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Storm drain, primary
Storm drain, smaller
Lake or tank
Metro lines (dashed: planned)
High-tension line, 765, 400, 220 and 66 kV
Its corridor, to scale
Buried cable
Approximate location: the filed pin, good to the neighbourhood, not the plot