Abhee Serenity Springs full report, Hennagara Main… | DOSL
This project 0 25 50 75 100 0 60 80 100 Percentile in Electronic City Clear 80–100 Review 60–79 Red flag, below 60DOSL Score Title – Approvals 100 Disputes Contract – Valuation Location 83 Construction 100 Developer 50 Loan – 0 60 80 100
Locked
Lapsed · completion date passed
Rajiv Gandhi Housing Corporation
323 sqft carpet (as filed)
A B Anantha Active · 84% built Amaravathi Builders Apartment 753–972 sqft carpet (as filed) Jan 2027
Abhee Nandika Completed · OC 22-04-2022 ABHEE DEVELOPERS Apartment 786 sqft carpet (as filed) Completed
Abhee Pride Completed · OC 18-04-2026 ABHEE VENTURES PRIVATE LIMITED Apartment 688–842 sqft carpet (as filed) Completed
Achalum Completed (regulator flag) ACHAL DEVELOPERS Plot ~1,200–2,400 sqft (estimate: filed carpet plus 25%) Completed
Other projects in Electronic City, A to Z
8 of 241 other projects in Electronic City, A to Z. Status is taken from each project's own filing.
2020 18 Feb 2020 Survey 16 Covers 16/1, 16/2A, 16/3, 16/5 only
Approval or registration
Land use converted
Deputy Commissioner · Survey 16/1, 16/2A, 16/3, 16/5
K-RERA filing, land schedule
27 Nov 2020 Survey 16 Covers 16/2B only
Approval or registration
Land use converted
Deputy Commissioner · Survey 16/2B
K-RERA filing, land schedule
2022 18 Feb 2022 Survey 16 Covers 16/4 only
Approval or registration
Land use converted
Deputy Commissioner · Survey 16/4
K-RERA filing, land schedule
2024 16 Nov 2024 Survey 16 Approval or registration
Khata issued
A Khatha · Hennagara Gram Panchayath · Survey 16/1, 16/2A, 16/2B, 16/3 and 2 more
K-RERA filing, land schedule
2025
14 Feb 2025 Project Title check
Records searched up to this date
Encumbrance certificate, p. 1 · See it in Documents
18 Feb 2025 Project Approval or registration
Building plan sanctioned
BMRDA · plan APA/CC/758/2024-25
K-RERA filing, approvals
18 Mar 2025 Project Approval or registration
RERA registration
PRM/KA/RERA/1251/308/PR/180325/007592
K-RERA registration · Open on the regulator's site
Approval or registration Title check The parcels join the project
Read from the original document Described in the filing or another document; the original is not read here
Boundaries Schedule in the EC vs KGIS neighbours Survey sketch Sketch, sanction and mutation vs KGIS map Land record The RTC of each filed survey Ownership Joint development agreement RERA Registration certificates Registration certificate PRM/KA/RERA/1251/308/PR/180325/007592
•••••
Unlock this full report ₹99 for this report opens Valuation, Disputes & cases and Documents for this project, yours to read for good.
Sign in to unlock for ₹99 Adjust maadbeda.One minute, read what Abhee Serenity Springs's developer filed before you say yes.
× Abhee Serenity Springs
Abhee Ventures · Hennagara Main Road, Bommasandra, Electronic City Phase 2
₹99 for this report
✓ Contract terms read from the filed agreement ✓ Title and land records read from the filings ✓ Every figure cited to its page ✓ Pay once. It stays yours to read Sign in first, then pay ₹99 once for this report. No subscription.
No spam calls. We never ask for your phone number.
Built from 100+ public records and registers, K-RERA filings first · No broker, no listing fees
Agreement for sale Form 4 certified totals •• %
•• ••• ••••
•••••
₹ •.•• Cr
Unit sizes Unit types
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
•• ••• ••••
Unsold stock K-RERA inventory
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
Registered deeds Transactions in this project The area Price trend North Bengaluru, past year Not verified yet
Bengaluru, past year Not verified yet
North since 2022 Not verified yet
This project vs North Bengaluru Not verified yet
Price per sq ft, super built-up Registered sales around Registered sale price per sq ft, by year Transactions around this project Comparable projects Carpet price, projects within 4 km Nearest 12 with filed prices
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
Nearest projects This project vs the nearest with filed prices
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
•• %
Rent & yield Rents and yields
₹ ••,•••
•• %
•• ••• ••••
•••••
₹ •.•• Cr
Unsold stock nearby Months to sell unsold stock K-RERA inventory
•• ••• ••••
•••••
₹ •.•• Cr
•• of ••
₹ ••,•••
Unlock this full report ₹99 for this report opens Valuation, Disputes & cases and Documents for this project, yours to read for good.
Sign in to unlock for ₹99 Adjust maadbeda.One minute, read what Abhee Serenity Springs's developer filed before you say yes.
× Abhee Serenity Springs
Abhee Ventures · Hennagara Main Road, Bommasandra, Electronic City Phase 2
₹99 for this report
✓ Contract terms read from the filed agreement ✓ Title and land records read from the filings ✓ Every figure cited to its page ✓ Pay once. It stays yours to read Sign in first, then pay ₹99 once for this report. No subscription.
No spam calls. We never ask for your phone number.
Built from 100+ public records and registers, K-RERA filings first · No broker, no listing fees
Around it Water Groundwater, Anekal taluk average 0 m 10 m 20 m 30 m 40+ m 10 to 20 20 to 40 Ten-year July mean for Anekal: 28.7 m Anekal taluk average, July 2023 21.3 m below ground 0 m 10 m 20 m 30 m 40+ m 5 to 10 10 to 20
0% 50% 100% Q3 2025-26: 13% 13% Q3 2025-26 Q4 2025-26: 18% 18% Q4 2025-26 Q1 2026-27: 25% 25% Q1 2026-27 Q2 2026-27: 35% 35% Q2 2026-27 0% 50% 100% Q3 2025-26: 13% 13% Q3 2025-26 Q4 2025-26: 18% 18% Q4 2025-26 Q1 2026-27: 25% 25% Q1 2026-27 Q2 2026-27: 35% 35% Q2 2026-27 0% 50% 100% Q3 2025-26: 13% 13% Q3 2025-26 Q4 2025-26: 18% 18% Q4 2025-26 Q1 2026-27: 25% 25% Q1 2026-27 Q2 2026-27: 35% 35% Q2 2026-27 0% 50% 100% Q3 2025-26: 13% 13% Q3 2025-26 Q4 2025-26: 18% 18% Q4 2025-26 Q1 2026-27: 25% 25% Q1 2026-27 Q2 2026-27: 35% 35% Q2 2026-27 As the promoter reported it
Work left By component, Q2 2026-27 Tower A Tower A: 22% 22% Tower B Tower B: 38% 38% Earth work and other leveling pr… Earth work and other leveling preparation work: 100% 100% Upto Plinth Level Upto Plinth Level: 100% 100% Retaining wall (All types) Retaining wall (All types): 90% 90% Main structure Main structure: 30% 30% Staircases Staircases: 30% 30% Corridor/Lobbies Corridor/Lobbies: 30% 30% Club House Not started Electricity Not started Outdoor Sports facility Not started Parks Not started
Tower A Tower A: 22% 22% Tower B Tower B: 38% 38% Earth work and other leveling pre… Earth work and other leveling preparation work: 100% 100% Upto Plinth Level Upto Plinth Level: 100% 100% Retaining wall (All types) Retaining wall (All types): 90% 90% Main structure Main structure: 30% 30% Staircases Staircases: 30% 30% Corridor/Lobbies Corridor/Lobbies: 30% 30% Club House Not started Electricity Not started Outdoor Sports facility Not started Parks Not started
Tower A Tower A: 22% 22% Tower B Tower B: 38% 38% Earth work and other leveling pre… Earth work and other leveling preparation work: 100% 100% Upto Plinth Level Upto Plinth Level: 100% 100% Retaining wall (All types) Retaining wall (All types): 90% 90% Main structure Main structure: 30% 30% Staircases Staircases: 30% 30% Corridor/Lobbies Corridor/Lobbies: 30% 30% Club House Not started Electricity Not started Outdoor Sports facility Not started Parks Not started
Tower A Tower A: 22% 22% Tower B Tower B: 38% 38% Earth work and other leveling pre… Earth work and other leveling preparation work: 100% 100% Upto Plinth Level Upto Plinth Level: 100% 100% Retaining wall (All types) Retaining wall (All types): 90% 90% Main structure Main structure: 30% 30% Staircases Staircases: 30% 30% Corridor/Lobbies Corridor/Lobbies: 30% 30% Club House Not started Electricity Not started Outdoor Sports facility Not started Parks Not started
Quarterly return, Q2 2026-27 Dates Dates 2025 2027 2029 Work began 28 Feb 2025 As of 31 Oct 2026 RERA deadline 30 Jun 2030 Builder's schedule ends 30 Jun 2030 Work began: 28 Feb 2025 As of 31 Oct 2026 RERA deadline: 30 Jun 2030 Builder's schedule ends: 30 Jun 2030
2025 2026 2027 2028 2029 2030 Work began 28 Feb 2025 As of 31 Oct 2026 RERA deadline 30 Jun 2030 Builder's schedule ends 30 Jun 2030 Work began: 28 Feb 2025 As of 31 Oct 2026 RERA deadline: 30 Jun 2030 Builder's schedule ends: 30 Jun 2030
2025 2026 2027 2028 2029 2030 Work began 28 Feb 2025 As of 31 Oct 2026 RERA deadline 30 Jun 2030 Builder's schedule ends 30 Jun 2030 Work began: 28 Feb 2025 As of 31 Oct 2026 RERA deadline: 30 Jun 2030 Builder's schedule ends: 30 Jun 2030
2025 2026 2027 2028 2029 2030 Work began 28 Feb 2025 As of 31 Oct 2026 RERA deadline 30 Jun 2030 Builder's schedule ends 30 Jun 2030 Work began: 28 Feb 2025 As of 31 Oct 2026 RERA deadline: 30 Jun 2030 Builder's schedule ends: 30 Jun 2030
Specified structure What the promoter specified · not an inspection Specified finishes Specification sheet · brands "or equivalent" Certificates Engineer, architect and fire certificates Estimated cost Land · ₹6.24 Cr: 4.6% Development · ₹129.49 Cr: 95.4% ₹136 Cr estimated cost Land · ₹6.24 Cr 4.6% Development · ₹129.49 Cr 95.4%
Sales Sold vs unsold, Q2 2026-27 Sold (110): 38.2% Unsold (178): 61.8% 38% 288 flats Sold (110) 38.2% Unsold (178) 61.8%
Flats sold per quarter Q4 2025-26 Q4 2025-26: booked flats went from 47 to 64 17 flats Q1 2026-27 Q1 2026-27: booked flats went from 64 to 90 26 flats Q2 2026-27 Q2 2026-27: booked flats went from 90 to 110 20 flats
Q4 2025-26 Q4 2025-26: booked flats went from 47 to 64 17 flats Q1 2026-27 Q1 2026-27: booked flats went from 64 to 90 26 flats Q2 2026-27 Q2 2026-27: booked flats went from 90 to 110 20 flats
Q4 2025-26 Q4 2025-26: booked flats went from 47 to 64 17 flats Q1 2026-27 Q1 2026-27: booked flats went from 64 to 90 26 flats Q2 2026-27 Q2 2026-27: booked flats went from 90 to 110 20 flats
Q4 2025-26 Q4 2025-26: booked flats went from 47 to 64 17 flats Q1 2026-27 Q1 2026-27: booked flats went from 64 to 90 26 flats Q2 2026-27 Q2 2026-27: booked flats went from 90 to 110 20 flats
Compliance Escrow, Q2 2026-27 Paid in Paid into the designated account in Q2 2026-27 ₹11.80 Cr Withdrawn Withdrawn by the promoter in Q2 2026-27 ₹8.98 Cr
Paid in Paid into the designated account in Q2 2026-27 ₹11.80 Cr Withdrawn Withdrawn by the promoter in Q2 2026-27 ₹8.98 Cr
Paid in Paid into the designated account in Q2 2026-27 ₹11.80 Cr Withdrawn Withdrawn by the promoter in Q2 2026-27 ₹8.98 Cr
Paid in Paid into the designated account in Q2 2026-27 ₹11.80 Cr Withdrawn Withdrawn by the promoter in Q2 2026-27 ₹8.98 Cr
Track record Average schedule slip This promoter, 4 other phases 4 completed and 0 extended: each filed date against the completion first promised 1 month Median of 1,753 phases Every phase in the corpus whose filing gives an extension or a completion 9 months
This promoter, 4 other phases 4 completed and 0 extended: each filed date against the completion first promised 1 month Median of 1,753 phases Every phase in the corpus whose filing gives an extension or a completion 9 months
This promoter, 4 other phases 4 completed and 0 extended: each filed date against the completion first promised 1 month Median of 1,753 phases Every phase in the corpus whose filing gives an extension or a completion 9 months
This promoter, 4 other phases 4 completed and 0 extended: each filed date against the completion first promised 1 month Median of 1,753 phases Every phase in the corpus whose filing gives an extension or a completion 9 months
Stage Progress as reported, by quarter Q3 2025-26 Q3 2025-26: 13% built, as the promoter reported it 13% Q4 2025-26 Q4 2025-26: 18% built, as the promoter reported it 18% Q1 2026-27 Q1 2026-27: 25% built, as the promoter reported it 25% Q2 2026-27 Q2 2026-27: 35% built, as the promoter reported it 35%
Q3 2025-26 Q3 2025-26: 13% built, as the promoter reported it 13% Q4 2025-26 Q4 2025-26: 18% built, as the promoter reported it 18% Q1 2026-27 Q1 2026-27: 25% built, as the promoter reported it 25% Q2 2026-27 Q2 2026-27: 35% built, as the promoter reported it 35%
Q3 2025-26 Q3 2025-26: 13% built, as the promoter reported it 13% Q4 2025-26 Q4 2025-26: 18% built, as the promoter reported it 18% Q1 2026-27 Q1 2026-27: 25% built, as the promoter reported it 25% Q2 2026-27 Q2 2026-27: 35% built, as the promoter reported it 35%
Q3 2025-26 Q3 2025-26: 13% built, as the promoter reported it 13% Q4 2025-26 Q4 2025-26: 18% built, as the promoter reported it 18% Q1 2026-27 Q1 2026-27: 25% built, as the promoter reported it 25% Q2 2026-27 Q2 2026-27: 35% built, as the promoter reported it 35%
1 km 3 km 2 km Bommasandra · 2.3 km 15 94 73 116 110 18 13 61 105 14 115 117 90 16 19 52 106 17 60 12 21 108 1 106 63 22 54 71 62 113 46 64 119 51 107 114 59 135 55 53 20 109 136 57 58 100 m Individual
Share as printed, Sy 16/2A 35
Owner as printed, Sy 16/2A ████████
Owner kind, Sy 16/2B Individual
Share as printed, Sy 16/2B 35
Owner as printed, Sy 16/2B ████████
Owner kind, Sy 16/2B Individual
Share as printed, Sy 16/2B 35
Owner as printed, Sy 16/2B ████████
Owner kind, Sy 16/3 Individual
Share as printed, Sy 16/3 35
Owner as printed, Sy 16/3 ████████
Owner kind, Sy 16/3 Individual
Share as printed, Sy 16/3 35
Owner as printed, Sy 16/3 ████████
Owner kind, Sy 16/3 Individual
Share as printed, Sy 16/3 35
Owner as printed, Sy 16/3 ████████
Owner kind, Sy 16/3 Individual
Share as printed, Sy 16/3 35
Owner as printed, Sy 16/3 ████████
Owner kind, Sy 16/3 Individual
Share as printed, Sy 16/3 35
Owner as printed, Sy 16/3 ████████
Owner kind, Sy 16/4 Individual
Share as printed, Sy 16/4 35
Owner as printed, Sy 16/4 ████████
Owner kind, Sy 16/4 Individual
Share as printed, Sy 16/4 35
Owner as printed, Sy 16/4 ████████
Owner kind, Sy 16/4 Individual
Share as printed, Sy 16/4 35
Owner as printed, Sy 16/4 ████████
Owner kind, Sy 16/4 Individual
Share as printed, Sy 16/4 35
Owner as printed, Sy 16/4 ████████
Owner kind, Sy 16/4 Individual
Share as printed, Sy 16/4 35
Owner as printed, Sy 16/4 ████████
Owner kind, Sy 16/5 Individual
Share as printed, Sy 16/5 35
Owner as printed, Sy 16/5 ████████
Owner kind, Sy 16/5 Individual
Share as printed, Sy 16/5 35
Owner as printed, Sy 16/5 ████████
Owner kind, Sy 16/5 Individual
Share as printed, Sy 16/5 35
Owner as printed, Sy 16/5 ████████
Owner kind, Sy 16/5 Individual
Share as printed, Sy 16/5 35
Owner as printed, Sy 16/5 ████████
Owner kind, Sy 16/5 Individual
Share as printed, Sy 16/5 35
Owner as printed, Sy 16/5 ████████
Area on the KGIS map Not verified yet
Land area of this registration 17,502 sq m
Khata A Khatha · Hennagara Gram Panchayath · 16 Nov 2024
500 m Basemap: Esri, OpenStreetMap contributors
Map of storm drains, lakes and government-flagged flood locations within about 900 m of the site.
20 to 40 Ten-year July mean for Anekal: 28.7 m Anekal taluk average, July 2023 21.3 m below ground 0 m 10 m 20 m 30 m 40+ m 2 to 5 5 to 10 10 to 20 20 to 40 Ten-year July mean for Anekal: 28.7 m Anekal taluk average, July 2023 21.3 m below ground 0 m 10 m 20 m 30 m 40+ m 2 to 5 5 to 10 10 to 20 20 to 40 Ten-year July mean for Anekal: 28.7 m Anekal taluk average, July 2023 21.3 m below ground Ten-year July mean for this taluk: 28.7 m
Across Anekal, the water table sat 21.3 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 28.7 m, and it recovered 3.3 m over the year.
Connectivity Road distance from the site Kempegowda Airport Kempegowda Airport: 58.1 km by road 58.1 km MG Road (CBD) MG Road (CBD): 23.8 km by road 23.8 km Manyata Tech Park Manyata Tech Park: 34.4 km by road 34.4 km ITPL, Whitefield ITPL, Whitefield: 29.1 km by road 29.1 km Ecospace, Bellandur ORR Ecospace, Bellandur ORR: 21.8 km by road 21.8 km Electronic City Ph 1 Electronic City Ph 1: 6.0 km by road 6.0 km
Kempegowda Airport Kempegowda Airport: 58.1 km by road 58.1 km MG Road (CBD) MG Road (CBD): 23.8 km by road 23.8 km Manyata Tech Park Manyata Tech Park: 34.4 km by road 34.4 km ITPL, Whitefield ITPL, Whitefield: 29.1 km by road 29.1 km Ecospace, Bellandur ORR Ecospace, Bellandur ORR: 21.8 km by road 21.8 km Electronic City Ph 1 Electronic City Ph 1: 6.0 km by road 6.0 km
Kempegowda Airport Kempegowda Airport: 58.1 km by road 58.1 km MG Road (CBD) MG Road (CBD): 23.8 km by road 23.8 km Manyata Tech Park Manyata Tech Park: 34.4 km by road 34.4 km ITPL, Whitefield ITPL, Whitefield: 29.1 km by road 29.1 km Ecospace, Bellandur ORR Ecospace, Bellandur ORR: 21.8 km by road 21.8 km Electronic City Ph 1 Electronic City Ph 1: 6.0 km by road 6.0 km
Kempegowda Airport Kempegowda Airport: 58.1 km by road 58.1 km MG Road (CBD) MG Road (CBD): 23.8 km by road 23.8 km Manyata Tech Park Manyata Tech Park: 34.4 km by road 34.4 km ITPL, Whitefield ITPL, Whitefield: 29.1 km by road 29.1 km Ecospace, Bellandur ORR Ecospace, Bellandur ORR: 21.8 km by road 21.8 km Electronic City Ph 1 Electronic City Ph 1: 6.0 km by road 6.0 km
Six city anchors · OSRM, no traffic Nuisances Distance from the site Sewage treatment plant Sewage treatment plant: 770 m 770 m Electrical substation Electrical substation: 1.1 km, Yerandanahalli Substation 1.1 km
Sewage treatment plant Sewage treatment plant: 770 m 770 m Electrical substation Electrical substation: 1.1 km, Yerandanahalli Substation 1.1 km
Sewage treatment plant Sewage treatment plant: 770 m 770 m Electrical substation Electrical substation: 1.1 km, Yerandanahalli Substation 1.1 km
Sewage treatment plant Sewage treatment plant: 770 m 770 m Electrical substation Electrical substation: 1.1 km, Yerandanahalli Substation 1.1 km
1 km 3 km 2 km Bommasandra · 2.3 km