Overview
Overview
Overview

Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | – | – | 1 | Clear |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Locked |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | 1 | Clear |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| 1 Lakh Multi - Storey Bengaluru Housing ProgrammeLapsed · completion date passed | Rajiv Gandhi Housing Corporation Limited | Apartment | 323 sqft carpet (as filed) | Apr 2023 |
| Adhya EnclaveLapsed · completion date passed | ADHYA DEVELOPERS | Plot | – | Dec 2023 |
| Affinity FidelityLapsed · completion date passed | SUDHAKARA REDDY ANNEM | Apartment | – | Jul 2022 |
| Affinity SarovarActive · 96% built | AFFINITY PROJECTS LLP | Apartment | 982–1,237 sqft carpet (as filed) | Sep 2027 |
| Alpine Pyramid EfghCompleted (regulator flag) | ALPINE HOUSING DEVELOPMENT CORPORATION LIMITED | Apartment | 1,066 sqft carpet (as filed) | Completed |
| ArenaLapsed · completion date passed | Marudhar Infra | Mixed development | 628–1,053 sqft carpet (as filed) | Sep 2024 |
| Arvind Orchards (Phase 1 + 2)Applied for completion 05/10/2026 | Arvind SmartSpaces | Plot | 1,500–2,400 sqft | Dec 2029 |
| Arvind Orchards Phase-2Active · 81% built | Arvind Smarthomes Private Limited | Plot | ~1,200–1,560 sqft (estimate: filed carpet plus 25%) | Dec 2029 |
8 of 89 other projects in Doddaballapur Road, A to Z. Status is taken from each project's own filing.
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open 99d By Santhusta in the interactive atlas
Title & ownership
₹99 for this report opens Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
Approvals
| Building plan (Doddaballapur Planning Authority) | Sanctioned 8 Jul 2025 · No. DPA/TP/LAO/05/2025-06 | |
|---|---|---|
| Power NOC (BESCOM) | Filed with the registration | |
| Fire NOC | Not verified yet | |
| SEIAA | Filed with the registration | |
| Airport height NOC | Not verified yet | |
| KSPCB | Filed with the registration | |
| Water supply NOC | Filed with the registration | |
| RERA extensions | None on the filing | |
|---|---|---|
| RERA complaints | 0 | |
| RERA completion date | 31 Jul 2028 |
| Land conversion | Converted 29 May 2025 · DC Rural | |
|---|---|---|
| Survey numbers | 35/1, 35/2A, 35/2B |
Disputes & cases
₹99 for this report opens Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
Contract & costs
₹99 for this report opens Contract & costs, Title & ownership and Disputes & cases for this project, yours to read for good.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Projects within 4 km, counted | 1 (1 with an approximate location) | |
|---|---|---|
| Flats in them | 201 | |
| Booked | 91 of 201 (45%) | |
| Unsold | 110 |
Location & risks
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Zoning, RMP 2015 | Not verified yet | |
|---|---|---|
| Nearest high-tension line | Not verified yet | |
| Nearest government-flagged flood location | about 22.5 km, Attur, Near Dairy Circle | |
| Height above nearest drain | Not verified yet | |
| Nearest storm drain | None within 3 km | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, an unnamed tank | |
| Height above nearest drain | Not verified yet | |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 31.2 m
Across Doddaballapura, the water table sat 20 m below ground in July 2023 (KSNDMC, a taluk average), shallower than the ten-year July mean of 31.2 m, and it recovered 4.7 m over the year.
| Groundwater | Doddaballapura taluk average, July 2023: 20 m below ground | |
|---|---|---|
| What it means | Not verified yet | |
| Water below ground | 20 m, the taluk average | |
| Through the year | Not verified yet | |
| Water supply, as filed | Borewell, Local authority (PDO) | |
| Nearest city water main | Not verified yet | |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Height above nearest drain | Not verified yet | |
|---|---|---|
| Nearest drain | None within 3 km | |
| Ground level | Not verified yet | |
| Metro, operational | Not verified yet | |
| Metro, under construction | about 18.5 km, Doddajala | |
| Kempegowda Airport | 33.5 | 23 |
| MG Road (CBD) | 44.5 | 37.5 |
| Manyata Tech Park | 37.5 | 31 |
| ITPL, Whitefield | 65 | 42.5 |
| Ecospace, Bellandur ORR | 60 | 45.5 |
| Electronic City Ph 1 | 64.5 | 54.5 |
| Landfill or waste transfer station | None within 3 km | |
|---|---|---|
| Sewage treatment plant | None within 3 km | |
| Quarry | None within 3 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 2 km |
Construction & progress
As the promoter reported it

| Main structure | Not verified yet | |
|---|---|---|
| Electrical and plumbing finishing | Not verified yet | |
| Internal roads | Not verified yet | |
| Club house | Not verified yet | |
| Completion | 100% | |
| Completion, accountant | Not verified yet | |
| Possession, agreement | Not verified yet | |
|---|---|---|
| Schedule end | Not verified yet | |
| RERA completion date | 31 Jul 2028 | |
| Work began, as filed | 10 Jul 2025 | |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Structural safety certificate | Not verified yet | |
|---|---|---|
| Structural engineer, quarterly | Form 6 · Mar 2026, Apr 2026, Jul 2026, Oct 2026 (4 filed) | Clear |
| Design consultants (Form 6) | Not verified yet | |
| Fire safety | Not verified yet | |
| Environmental clearance | Not verified yet | |
| Engineer's certificate, registration | Dated 8 Jul 2025 | |
| Chartered accountant's certificate, registration | Dated 24 Jul 2025 | |
| Chartered accountant, Form 4 | Dated 14 Jul 2026 | |
Developer
Land · ₹23.88 Cr 54.1%Development · ₹20.22 Cr 45.9%
| Estimated cost | ₹44.10 Cr | |
|---|---|---|
| Estimated cost, engineer's certificate | ₹18.00 Cr | |
| Cost incurred | ₹1.19 Cr | |
| Cost left | Not verified yet | |
| Collected from buyers | Not verified yet | |
| Receivable, sold flats | Not verified yet | |
| Land cost revision | Not verified yet | |
| Flats booked, Form 4 Q1 2026-27 | 15 |
|---|
| Escrow bank | Karnataka Bank Ltd. · Sadashiva Nagar, Bangalore | |
|---|---|---|
| Designated account, collected | ₹3.82 Cr in Q2 2026-27 | |
| Designated account, withdrawn | ₹1.05 Cr in Q2 2026-27 (27% of that quarter's deposits) | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| RERA complaints | 0 | |
Loan & collateral
| Developer's project loan | No borrowing declared | |
|---|---|---|
| Records searched to | Not verified yet | |
| Building plan | Sanctioned 8 Jul 2025 | |
| Unregistered agreements, over 10% paid | Not verified yet | |
| Sale deed in favour of | Not verified yet | |
| Escrow bank | Karnataka Bank Ltd. · Sadashiva Nagar, Bangalore | |

Data room
Source: K-RERA project page and the documents filed there, as read by us. 53 documents filed with K-RERA, identity papers and photographs, are left out of this list.